BESCOM Estimate Generator

Estimate
Work & beneficiary
Network

Poles = length ÷ span, rounded up. Conductor (km) = wires × length × (1 + sag%) ÷ 1000. With your samples: 460 m → 10 poles and 1.401 km; a 20 m LT line → 1 pole and 0.082 km.

Signatories

Start typing a particular to pick it from the Common SR 2025-26 rate list; that fills in the unit, material rate and labour rate. ↳ makes a row a sub-item of the row above, like item 12 i/ii/iii in Part-B. L charges that row's labour as a lump sum instead of rate × qty.

Abstract (Common SR 2025-26, Table-1)

Following the 13-04-2026 order: ASL is charged on labour only. OH and CP are each charged on Sl. 1–3, never on each other. GST is charged on Sl. 6. The grand total is rounded to the nearest rupee.

Sketch
Route of the 11kV line from A (tapping point) to B (DTC). The legs should add up to the 11kV length.
Title paragraph

Placeholders: {work} {name} {rel} {father} {village} {section} {subdiv} {scheme} {gkid} {lat} {lng} {syno}. Use **bold** and __underline__.

Report

Also: {ht} {lt} {kva} {feeder} {muss} {mussRating} {hp} {total} {totalWords}.

Sanction stamp
HT voltage regulation page

HTVR % = Total KVA·KM × constant ÷ (factor × 100). Each segment's KVA·KM = all load at and beyond its far node × its length. Your samples use 0.0636 with factor 1.5 (estimation 2) or factor 1 (63 kVA estimate).

Feeder segments (from substation outward)
The node farthest from the substation is A. Load = existing DTC kVA at that node.
NodeLength (km)Load (kVA)
Generating PDF…